A meeting was advertised by the FKAA and approxiamately 100 residents attended. A Power Point presentation was given.

The content displayed during the presentation is provided below. Pictures showing typical construction that were part of the presentation are not shown here.

The presentation was followed by a lengthy Question and Answer Period. No attempt to reduce the Q and A  into written form is provided here.


 

Wastewater Staff

  • Jim Reynolds - FKAA
  • Kerry Shelby - FKAA
  • Ray Shimokubo - FKAA
  • Kirk Zuelch - FKAA  
  • George Garrett - Monroe County
 

 

Meeting Objective

  •  Explain why FKAA is nvolved
  •  Summarize the proosed wastewater program
  •  Describe current schedule
  •  Discuss project financing
  •  Question and answers 

 


 
  • Why FKAA is Involved
  • State Law mandates the Florida Keys must be   served by sewer systems by 2010
  • FKAA has the authority to implement wastewater systems in the Florida Keys (unincorporated County)
  • Duck POA has requested FKAA to initiate implementation of the system
  • FKAA is acting on behalf of POA

     


    Recent Developments

  • FKAA is in the process of finalizing the agreement to acquire the Hawk's Cay WWTP
  • The Conch Key wastewater system  construction will commence in May 2004
  • Monroe County has requested that the WWTP  be upgraded as soon as possible
  • Planned properly, this will allow Duck Key to use the WWTP   
  • These developments make it favorable to Duck Key to move forward

 

 


  • Duck Key Wastewater System

  • Central wastewater system including:

    - Duck Key
    - Hawk's Cay
    - Conch Key 
     

  • As described in the Monroe County Wastewater Plan 
     
  • Duck Key system will include:

    - Wastewater collection system
    - Treatment at Hawk's Cay WWTP

 


Duck Key Wastewater System

  • Approximately 380 EDUs
  • Wastewater Collection System

    - Gravity Systems
    - Vacuum Systems

  • Wastewater Treatment Plant (WWTP) Options

    - Advanced Wastewater Treatment (AWT) at Hawk's Cay

     

     


    Profile Detail of Typical Building Connection

Wastewater system image

Duck Key and Conch Key Wastewater Project Schedule

FKAA wastewater project schedule

 

 
 Planning and Development Funding
  • Municipal Services Taxing Unit (created by Monroe County)

    Currently 5 MSTUs in Monroe County (Conch Key, Bay Point, Marathon, Big Coppitt and Key Largo
    Most are about .7 mil for 4 year period for planning (with remaining funds available for capital)

  • Monroe County
  • Federal and State sources

     


     

    Estimated Project Costs and Financing Sources

  • Total estimated project costs are $5-7 million
  • Grant funding directly offsets the costs to customers
  • Financing expected through tax exempt financing or state revolving fund

     


     

    What do you pay?

  • System Development Charge for your share of the project's capital costs -
    - Based on Equivalent Dwelling Units (EDUs) -
    - Payable either in full or over 20 years through a non ad valorem assessment on your annual tax bill
  • Cost of Installing your lateral to connect to the system at the street
  • Monthly User Charge for operation of the system
 

 